PROSJEKTINFORMASJON:
-
Systemtype: Bakkeanlegg – Solcellepark.
- HIM Solar park is constructed at Toraneset miljøpark, located outside Haugesund. HIM Toraneset ise the first large-scale ground mounted solar park in the region. The plant will deliver 2.7 GWh of electricity to the grid annually – equivalent to the electricity consumption of about 160 households. HIM Toraneset Solar Park is a collaboration with Haugaland Interkommunale Miljøverk (HIM), which is commissioning a new landfill site. The former landfill will be decommissioned and monitored for 30 years as required. During this time, the area will be repurposed for renewable energy production – turning otherwise unused land into a long-term contributor to the green transition.
-
Progress plan
- Mechanically completed September 2025
- Construction start March 2025
- Permit approved by NVE: June 2024
- Permit application submitted: June 2023
-
SJ SOL AS IS EPC